The lower lot is excavated and ready for a pair of 2-bedroom vacation villas.The upper lot, likewise is excavated, leveled and ready for a dream home.We even have a driveway.
September 2024
Foundations are framed, plumbing is stubbed, we’re ready to pour cement in the lower-level villas.Those big holes adjacent to the villas? Those are private swimming pools for our guests!The upper-level dream home, framed, stubbed, ready and waiting for the cement truck.
October 2024
Just like that, lower level villa has a foundation.Upper lot too!It doesn’t look like much now, but that’s going to be an inviting swimming pool.The upper level dream home is all cemented up. Three days to cure and they can start erecting walls. Woo hoo!